Bug Report [Back] [Home] [Next]
 

Home
What's New
Model and Data Files
Manuals/Tutorials
F.A.Q.
Suggestions
Bug Report
Known Issues
About SRCE
Contact Us

LAST UPDATE: July 21, 2006

 

Version 1.0


Version 1.0


Exploration & Well Abandonment Modules - Drillhole plugging costs do not calculate correctly when multiple holes are open at one time for Exploration Drillholes (Exploration) or Monitor Wells (Well Abandonment).

This problem occurs due to the minimum hours calculation. It occurs when:

      1) the calculated plugging (abandonment) hours per hole is less than 2 hours;

                                                         and

      2) you enter a number greater than 1 in the "Max Holes Open at One Time"

If the total hours to plug all of the holes is greater than 2 hours, then the model incorrectly ignores the minimum 2 hour/hole requirement (1 hr. move to/setup/tear-down + 1 hr minimum). If more than one hole is open at one time, the model should determine if there is a minimum of 2 hours per hole and, if not, multiply the number of holes by 2 hours (e.g. 25 holes should require a minimum of 50 abandonment hours).

This will be fixed in the next release.

Work-around: Enter each hole that will be open on a separate line.

Severity: minor

Impact: very minor (unless large numbers of exploration holes are left open at one time)

Back to Top

All Modules - When User Mix 5 is selected as the seed mix, revegetation material costs are not calculated.

This problem occurs due to the fact that the range used to match the costs with the selected seed mix has an error.

It occurs when User Mix 5 is selected even though a material cost is shown for this seed mix. on the Materials Costs worksheet.

User Mix 5 is calculated from the Seed Mixture worksheet. It then appears on the Materials Costs worksheet as a calculated value. When this seed mix is selected in one of the worksheets, the model looks in the wrong cell for that value and enters an null value.

This will be fixed in the next release.

Work-around: Use one of the other User Seed Mixes. If you need to use the Seed Mixture worksheet to calculate the seed mix costs, do so but then enter the same cost in one of the other User Seed Mix cost cells on the Materials Costs worksheet and select that seed mix in the other spreadsheets.

Severity: minor

Impact: very minor because other User Seed Mix options can be used.

Back to Top

Pits Module - Revegetation material costs are not carried forward to the Cost Summary worksheet.

This problem occurs because the revegetation option for pit berms was added to Version 1.0 at the 11th hour and the link to the Cost Summary worksheet was not modified. This ONLY affects material costs.

The total labor and equipment costs for both earthworks and revegetation activities are carried forward into the respective cells in the Earthworks section of the Cost Summary worksheet. This means that no revegetation equipment or labor costs will appear in the Revegetation section of the Cost Summary worksheet. However, these costs are included in the Total Operations & Maintenance Costs line of the Cost Summary worksheet.

This will be fixed in the next release.

Work-around: Use the Material Cost cell in one of the **Other rows (under either the Earthworks section or Revegetation section) of the Cost Summary worksheet to include the Revegetation Materials costs from the Pits worksheet. You DO NOT need to transfer the Revegetation Equipment or Labor costs from the Pits worksheet. Although this somewhat inelegant, the bond will calculate correctly using this work-around.

Severity: minor

Impact: minor if work-around described above is used.

Back to Top

Sediment & Drainage Control Module - Diversion Ditch revegetation costs are not carried forward to the Cost Summary worksheet.

This problem occurs because the revegetation option for Diversion Ditches was added to Version 1.0 at the 11th hour and the link to the Cost Summary worksheet was not modified. This ONLY affects Diversion Ditch revegetation costs. The Sediment/Evaporation Pond revegetation costs do carry forward properly.

None of the revegetation costs (labor, equipment and material) for Diversion Ditch are carried forward into the respective cells in the Revegetation section of the Cost Summary worksheet.

This will be fixed in the next release.

Work-around: Use the cells in the **Other row under Revegetation section of the Cost Summary worksheet to include the Diversion Ditch revegetation costs from the Sediment & Drainage Control worksheet. Although this somewhat inelegant, the bond will calculate correctly using this work-around.

Severity: minor

Impact: minor if work-around described above is used.

Back to Top

Cost Summary Module - Indirect line item costs are not removed from the Subtotal Add-On Costs line when line item check boxes are unchecked.

This problem occurs when a user tries to remove line item indirect costs by unchecking the check box next to line item in question. The formula in the Subtotal Add-On Costs cell is referring to a hidden cell that does not subtract the unchecked line items.  The indirect cost adjustments for Small Plans and Private Land bonds costs do work properly.

Because all of these indirect costs are required on public lands in the U.S. and private land in Nevada, this problem will only affect bonds calculated for projects on private lands outside the state of Nevada and projects outside the U.S.

This will be fixed in the next release.

Work-around: None available in the model. The user can take the total indirect costs from the Total Operations & Maintenance Costs line and then add appropriate indirect costs manually.

Severity: minor

Impact: moderate because this may affect overseas projects and projects outside of the U.S.

Back to Top

Exploration Roads & Pads Module - When using the user override option for regrade volume, the costs are doubled.

This problem occurs when a user tries to use the override value for regrading volume in the first user input table. This problem occurs because an error in the model assumes that the override volume applies to both the road and pad regrading portions of the calculation, thereby doubling the total volume. 

This will be fixed in the next release.

Work-arounds: Either do not use the user override or input 1/2 of the desired volume. If you use the second option, you can check the Total Volume column in the Regrading table to make sure the model is using the correct volume. 

Severity: minor

Impact: minor if work-around described above is used.

Back to Top

Well Abandonment Module - Costs for inert material placement in Monitor Wells are not included in the Cost Summary at the top of the page.

This is an error in the Cost Summary at the top of the Well Abandonment module. The labor and equipment costs for inert material placement are not included in the summary table. 

This will be fixed in the next release.

Work-arounds:  Manually add these costs from the Well Abandonment (Monitor Wells) module to the cost summary in the Other line in Section A of the Cost Summary Page

Severity: minor

Impact: minor if work-around described above is used.

Back to Top

Project Information Module - After selecting region other than first region, user cannot see other region names.

This was caused when extra rows were inadvertently added to the range during final edits to Version 1.0.  If a user selects a region below the first region, all other regions above that selection will scroll up and no longer be visible when re-entering that box. However, if the user scrolls up in the list (using the scroll bar on the right side of the dropdown menu or arrow keys), the regions above will become visible and accessible for selection.

The "#N/A" entries in the bottom rows are irrelevant. Only those cells with actual region names and descriptions are valid.

This will be fixed in the next release.

Work-arounds:  Scroll up in the dropdown menu using the scroll bar on the right side of the menu or the up/down arrow keys.

Severity: very minor

Impact: very minor

Back to Top

User Data File - After importing User Data #VALUE errors appear in calculation cells even after the user selects a "Region" and Labor Zones.

There must be an entry for at least one Zone and Zone Rate for each Region Used in each of the three labor classifications (Equipment Operators, Truck Drivers, Laborers). The model requires a non-blank entry in the Labor Zone for each Labor Category  in the Labor Rates Module:

.

This may be modified in the next release.

Work-around: 

In the Standard Cost Data file, these zones are already entered. If you want to use your own cost data using the CostDataUSR.xls file, then you need to enter this data in that file before importing it to the Model. The example below shows the Zone Adjustments for the Power Equipment Operators in the User Cost data file. The Zone is defined as "none" and the adjustment is $0.00. This will create a dropdown option of "none" with a $0.00 adjustment in the Labor Rates Module of the SRCE Model once you reload the User Data cost file. You only need to enter this for one zone, but you must enter at least one zone for each of the labor categories (Power Equipment Operators, Truck Drivers and Laborers).

Severity: minor

Impact: minor if work-around described above is used.

Back to Top

Exploration Roads & Pads Module - Regrade volumes are overestimated.

This problem occurs because of an error in the volume calculation for the road portion of the total regrade volume. The formula should be:

            Total Regrade Volume = (Road Cross-Sectional Area x Road Length) + (Drill Pad Cross-Sectional Area x Total Drill Pad Length)

            where: Road Length = Total (Road+Drill Pad) Length - Total Drill Pad Length

                       Drill Pad =  Total (Road+Drill Pad) Length - Road Length

Unfortunately, the current formulas do not correctly calculate the Road Length [i.e. they do not subtract the Total Drill Pad Length from the Total Length (Road + Total Drill Pad)]. This will cause the regrade volume to be overestimated by the difference of the Drill Pad Cross-Sectional Area and the Road Cross-Sectional Area times the Total Drill Pad Length. Depending on the difference in the width of the road and the drill pad, and the total length of the Drill Pads, this overestimate may or may not be significant. The greater the road length and smaller the number of drill pads, the smaller the overestimate will be. Also, if the underlying slope is fairly gentle, the overestimate will be smaller.

For example, using the following inputs the total volume overestimate is approximately 20%:

          Total Length (Roads+Drill Pads) = 2100

          Width of Road = 19

          Number of Drill Pads = 12

          Size of Drill Pads = 30 x 75

          Original (underlying) slope = 56%

          Ungraded slope = 1.3H:1V

          Cut Slope = 70%

When these inputs were used for an actual small exploration bond cost estimate, it resulted in a 14% overestimate of total costs, but the total road + pad length was nearly 1/2 drill pads.

This will be fixed in the next release.

Work-arounds: Enter the road portion and total drill pad portions for each roads/drill pad segment on separate lines as shown below:

In some cases, the total cost increase will not be significant enough to justify this effort.

Severity: moderate

Impact: minor, but annoying if work-around described above is used.

Back to Top

Error Message on Startup - A warning message stating "This file contains macros with and expired or revoked signature..." or a dialog box opens on startup stating "A certificate (signing or issuer) has expired" appears when the model is opened.

First: The code signing certificate WAS renewed. It has NOT been revoked.

This problem occurs because Microsoft, in their infinite wisdom, does not include a Timestamp option in VBA for office applications. Time stamping allows your computer to check to see if the certificate was valid when the code was signed. Since Microsoft does not have this option, your computer looks to see if the code signing certificate is currently valid. Since the certificates are good for one year, the certificate officially expired on March 20, 2006. When the certificate was renewed (before March 20), we were issued a new certificate number. Therefore, Excel thinks this certificate is expired.

Fortunately, VeriSign (our certificate provider) has provided us with a time stamping work-around that will allow us to include a time stamp with any future versions. In the meantime you need to follow these steps:

IF YOU SEE AN EXCEL WARNING LIKE THIS:

 

It means you will have to change the Macro Security setting in Excel to do this:

     1. Then select the "OK" button to close this dialog box.

     2. Select the "OK" button on the next dialog box. This will open the model with all macros disabled. It WILL NOT work properly in this mode.

     3. Open the Tools/Options menu in Excel as shown:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

     4: Select the "Macro Security" button on the "Security" tab:

 

 

 

 

 

 

 

 

 

 

 

     5. Set the Security Level to "Medium" in the Security dialog box. This will not automatically allow potentially dangerous macros to run on your computer, but it will give you the option to run ones that you know are safe (like the ones in the SCRE model):

 

 

 

 

 

 

 

 

     6: Close and restart the Model and Excel. When you do: you will see the dialog box shown below. Proceed to Step 7.

IF YOU SEE THE FOLLOWING DIALOG BOX:

     7: Select the "Enable Macros" button. As stated above, the macros are safe as long has you have not tampered with the file.

This will be fixed in the next release.

Work-around: Set Excel Macro Security to "Medium" as described above

Severity: minor

Impact: minor

Back to Top
 

Exploration Roads & Pads Module - Grading and Revegetation Total Surface Area rounds to nearest acre.

The cell containing the Total Surface Area cell in the Grading and Revegetation Table is set to round to the nearest acre. The surface acres for each facility are rounded to the nearest 1/10th acre. This DOES NOT affect any of the cost calculations and is therefore only a formatting issue. 

This will be fixed in the next release.

Work-around: Not necessary. 

Severity: Insignificant

Impact: None.

Back to Top

Sediment & Drainage Control Module - A Pond Info! message appears when the Liner Type cell is left blank for sediment ponds.

This error message appears when a user leaves the Liner Type cell blank. It DOES NOT affect the cost calculations and only causes the earthwork correction factors, productivities and hours to be overwritten by the error message.

This will be fixed in the next release.

Work-around: Not necessary 

Severity: Insignificant

Impact: None on cost calculations, very minor on formatting.

Back to Top

Exploration Module - A rounding function in the calculations may cause slight deviations in cost per hole when multiple holes are left open.

Because of the way the detailed volumetric and hour calculations are rounded, the cost per hole can vary (and therefore the total as well) when more than one hole is entered in the Max Holes Open at One Time cell. This may cause a different total to be calculated if each hole is entered on a separate line rather than including multiple holes on a separate line.

This will be fixed in the next release.

Work-around: Because the rounding will only create minor differences, in most cases none is needed. If needed, enter each hole on a separate line. Because this may require significant extra work for a minor cost change, this may not be justified. 

Severity: very minor

Impact: very minor.

Back to Top

Roads Module - A Select Fleet message appears appears in the Regrading Costs table when the regrade volume = 0.

This error message appears when the Regrade volume for a road or road segment = 0. This could be the result of using a 0% original slope or by entering in 0 in the user override cell for volume in the first user input table. This message DOES NOT affect the cost calculations.

This will be fixed in the next release.

Work-around: Not necessary 

Severity: Insignificant

Impact: None on cost calculations, very minor on formatting.

Back to Top

Foundations & Buildings Module - The slab demolition cost in the summary table is not included in the Demolition Subtotal and therefore does not get included in the Cost Summary Module.

This problem is caused by an error in the formulas used to subtotal the demolition costs at the top of the Foundations & Buildings module. Because the Slab Demolition costs ARE NOT included in the Cost Summary Module either. Therefore, this error WILL affect the final cost calculations.

This will be fixed in the next release.

Work-around: Manually add the Slab Demolition labor and equipment costs from the Cost Summary table at the top of the Foundations & Buildings module to the Other line item in the Structure, Equipment and Facility Removal section (Section D) of the Cost Summary Module. This can be done by copying the numbers from the Foundations & Buildings Module or by inserting a formula in the Other line item for both labor and equipment costs.

For example the formula for the Labor cell would be: ='Foundations & Buildings'!C12

Severity: Serious if work-around is not used

Impact:  Significant if foundations are included in the bond cost estimate..

Back to Top

Foundations & Buildings Module - A Wall Type! message appears in the Demolition Costs table when the Foundation Wall Type cell is left blank.

This error message appears in the Demolition Costs table when the Foundation Wall Type cell is left blank. This message DOES NOT affect the cost calculations.

This will be fixed in the next release.

Work-around: Not necessary 

Severity: Insignificant

Impact: None on cost calculations, very minor on formatting.

Back to Top

LAST UPDATE: July 21, 2006


If you're experiencing a problem with the SRCE Model, please fill out and submit a bug report form.

For suggestions, or requests for improvements, please use our suggestion form.

Information on bug reports and suggestions may be shared with the contributors to the Nevada Standardized Unit Cost Project to assist us in future development planning. However, this information will not be shared with other parties or used for marketing purposes.


    

 


[Home] [What's New] [Model and Data Files] [Manuals/Tutorials] [F.A.Q.] [Suggestions] [Bug Report] [Known Issues] [About SRCE] [Contact Us]

Questions or problems regarding this web site or the SRCE model should be reported using the Bug Submission Form.
[ top ]

Copyright © 2004 -
Jeffrey V. Parshley. All Rights Reserved.